Calgary, Alberta--(Newsfile Corp. - March 13, 2024) - Fathom Nickel Inc. (CSE: FNI) (FSE: 6Q5) (OTCQB: FNICF) (the "Company" or "Fathom") is pleased to announce that drilling has been completed at the Company's 100% owned Albert Lake Project and that drill, and crews have mobilized to the Gochager Lake Project. Drilling commenced at the Gochager Lake Project on March 12 and is expected to continue through mid-April 2024.
Summary of the Albert Lake Project drill program is as follows:
- Six (6) holes were drilled amounting to 1,386 meters drilled (Figure 1).
- Drillhole AL24075, the first drillhole of the program was designed to test the very robust EM-coincident gravity anomaly. The drillhole intersected multiple zones of elevated sulphide mineralization from 295.0 - 348.5m. The host rock was not mafic/ultramafic in composition and pXRF scans of the mineralization suggest the mineralization is not that of a magmatic sulphide source.
- The semi-massive to locally massive sulphide mineralization hosted within sediment hosted sulphidic iron formation does explain the strong EM conductivity and the gravity feature targeted.
- The other five (5) drillholes focused on weaker EM features coincident with local strong multi-element soil geochemistry results. Multiple zones of varying conductivity were identified by BHEM surveys and within the detailed EM grids surveyed during the program. Several of these zones coincide with interpreted mafic/ultramafic intersections from the drilling and are worthy of more follow-up surface exploration and drilling.
- Assay results are expected by mid-late April 2024 and the Company will provide a complete summary of the Albert Lake program once assays are in hand.
Ian Fraser, CEO and VP Exploration stated, "Although we are disappointed the significant sulphide mineralization encountered in the first drillhole appears to be not magmatic in origin, we are encouraged that the remainder of the drill program did identify several, shallow weak to moderate zones of conductivity by BHEM and by our detailed surface EM grids. Some of these zones are coincident with zones of mafic - ultramafic rock intersected in our drill program. However, the robust soil geochemical anomaly that was our focus remains unexplained and eminently worthy of future exploration. Given the shallow nature of several of these new targets (<100m below surface) it is suggestive that this anomaly is perhaps a culmination of several shallow sources. In this new scenario we felt further detailed surface work is required to target them appropriately. Furthermore, drilling these new, shallow targets with a helicopter supported drill would be a very inefficient use of exploration dollars and investor capital. Based on this, the Company made the decision to cut the Albert Lake Project drill program short of the intended meterage and use these "extra" meters at the Gochager Lake Project drill program. Future drilling of these new, shallow Albert Lake targets will utilize a smaller, track or skid mounted drill providing a greater degree of flexibility and in the process a much more costs effective approach versus the helicopter supported methodology deployed in the most recent drill program."
Figure - 1 Albert Lake Project Drillhole Plan Map
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/7843/201526_3b57106404ddaafd_001full.jpg
Gochager Lake Drill Program:
- Drilling commenced on March 12.
- The Company anticipates drilling 2000-2500 meters in 5-7 drillholes.
- Initial drillholes are designed to follow-up on nickel-copper-cobalt mineralization encountered in drillhole GL23009 (see Press Release November 21, 2023) and the associated off-hole BHEM conductivity detected in this drillhole (Figure 2).
- New zones of conductivity resulted from additional surface TDEM survey performed southwest of the Gochager Lake deposit in February 2024. Follow-up, detailed TDEM survey in this area will commence on March 14.
- Several new, high-priority drill targets have been identified outside the area of the historic Gochager Lake deposit.
Ian Fraser, CEO and VP Exploration stated, "We are very excited to get back to the historic Gochager Lake deposit and continue to build out this deposit and increase tonnes and grade in the process. The current program is designed to drill multiple holes with a common azimuth across the host Gochager Lake intrusive and to specifically test zones of off-hole BHEM conductivity that resulted from the Fall 2023 drill program. Our 2023 drill programs illustrated zones of BHEM conductivity contained zones of nickel mineralization grading >1% Ni and these higher-grade zones have a steep orientation and plunge. The 9-holes drilled in 2023 provided an initial good understanding of the dynamics of the historic Gochager Lake deposit and we look forward to continuing to build on this understanding. Ongoing interpretation of geophysical data collected in 2023-2024 along with historical data confirms that the historic Gochager Lake deposit is wide open along strike northeast, southwest and to depth. This current drill program will expand upon the 2023 results along strike and to depth and we are confident will add another dimension on our path to a new, modern maiden resource for the Gochager Lake deposit. We look forward to continuing the drilling success we had in 2023."
Figure - 2 Initial Drill Cross-Section Gochager Lake Drill Program
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/7843/201526_3b57106404ddaafd_002full.jpg
Comments on Initial Drillhole, Cross Section
- The grade shells (>0.2% Ni, >0.5% Ni) are based on Fathom 2023 drilling and are at present best approximation / interpretation of steeply oriented mineralized envelope(s) defined to date.
- It is within these mineralized envelopes (>0.5% Ni) in which the Company intersected multiple zones of >1% nickel + significant cobalt mineralization. See Press Release November 21, 2023.
- Complex off-hole BHEM responses were detected in GL23009 from ~335-370m. These zones of conductivity are interpreted to be typical of semi-massive to massive sulphides and it has been suggested this is possibly a discrete zone separate from the semi-massive sulphides intersected above the interpreted fault.
- The initial drillhole of the March 2024 Gochager Lake drill program is designed to test this area of complex BHEM conductivity and extend the mineralization intersected in GL23009 down plunge to depth and along strike.
- Also of note, increasing conductivity in GL23009 was observed building to depth beyond the end of drillhole. Furthermore, the massive sulphide vein intersected in GL23008 (3.25% Ni / 0.64m) is within 40m of the proposed drillhole, and as in GL23009, conductivity builds to depth and beyond drillhole GL23008.
- The initial drillhole will be drilled deep enough to test the source of building conductivity at depth.
Qualified Person and Data Verification
Ian Fraser, P.Geo., CEO, VP Exploration, and a Director of the Company and the "qualified person" as such term is defined by National Instrument 43-101, has verified the data disclosed in this news release, and has otherwise reviewed and approved the technical information in this news release on behalf of the Company.
About Fathom Nickel Inc.
Fathom is an exploration company that is targeting magmatic nickel sulphide discoveries to support the rapidly growing global electric vehicle market.
The Company now has a portfolio of two high-quality exploration projects located in the prolific Trans Hudson Corridor in Saskatchewan: 1) the Albert Lake Project, a 90,000+ hectare project that was host to the historic and past producing Rottenstone deposit (produced high-grade Ni-Cu+PGE, 1965-1969), and 2) the 22,000+ hectare Gochager Lake Project that is host to a historic, NI43-101 non-compliant open pit resource consisting of 4.3M tons at 0.295% Ni and 0.081% Cu2.
1 - The Saskatchewan Mineral Deposit Index (SMID#0950) Tremblay-Olson Ni-Cu Deposit or Showing
2 - The Saskatchewan Mineral Deposit Index (SMID#0880) reports drill indicated reserves at the historic Gochager Lake Deposit of 4,262,400 tons grading 0.295% Ni and 0.081% Cu mineable by open pit. Fathom cannot confirm the resource estimate, nor the parameters and methods used to prepare the reserve estimate. The estimate is not considered NI43-101 compliant and further work is required to verify this historical drill indicated reserve.
ON BEHALF OF THE BOARD
Ian Fraser, Chief Executive Officer and Vice-President, Exploration
1-403-650-9760
Email: ifraser@fathomnickel.com
or
Doug Porter, President & CFO
+1-403-870-4349
Email: dporter@fathomnickel.com
Forward Looking Statements:
This news release contains "forward-looking statements" that are based on expectations, estimates, projections and interpretations as at the date of this news release. Forward-looking statements are frequently characterized by words such as "plan", "expect", "project", "seek", "intend", "believe", "anticipate", "estimate", "suggest", "indicate" and other similar words or statements that certain events or conditions "may" or "will" occur, and include, without limitation, statements regarding intended future exploration work, including drilling, and the timing of such activities. Forward-looking statements relate to information that is based on assumptions of management, forecasts of future results, and estimates of amounts not yet determinable. Any statements that express predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be "forward-looking statements." Forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation: risks related to failure to obtain adequate financing on a timely basis and on acceptable terms; risks related to the outcome of legal proceedings; political and regulatory risks associated with mining and exploration; risks related to the maintenance of stock exchange listings; risks related to environmental regulation and liability; the potential for delays in exploration or development activities or the completion of feasibility studies; the uncertainty of profitability; risks and uncertainties relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits; risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; results of prefeasibility and feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; risks related to commodity price fluctuations; and other risks and uncertainties related to the Company's prospects, properties and business detailed elsewhere in the Company's disclosure record. Such forward looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. These forward-looking statements are made as of the date hereof and the Company does not assume any obligation to update or revise them to reflect new events or circumstances except in accordance with applicable securities laws. Actual events or results could differ materially from the Company's expectations or projections.
NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES. ANY FAILURE TO COMPLY WITH THIS RESTRICTION MAY CONSTITUTE A VIOLATION OF U.S. SECURITIES LAWS
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/201526
SOURCE: Fathom Nickel Inc.