Anzeige
Mehr »
Freitag, 13.02.2026 - Börsentäglich über 12.000 News
Top-Ergebnisse: 1,75 g/t Gold über 30,4 Meter + massives Tagebau-Potenzial
Anzeige

Indizes

Kurs

%
News
24 h / 7 T
Aufrufe
7 Tage

Aktien

Kurs

%
News
24 h / 7 T
Aufrufe
7 Tage

Xetra-Orderbuch

Fonds

Kurs

%

Devisen

Kurs

%

Rohstoffe

Kurs

%

Themen

Kurs

%

Erweiterte Suche
PR Newswire
543 Leser
Artikel bewerten:
(2)

Hydrogen Council: Global hydrogen industry reports $75 billion in committed capital but climate targets at stake due to project delays

BRUSSELS, Sept. 17, 2024 /PRNewswire/ -- The global clean hydrogen project pipeline is growing and maturing, with a sharp increase in projects reaching final investment decision (FID), according to the Hydrogen Council's latest analysis of more than 1,500 projects worldwide. At the same time, the pace and scale of deployment need to accelerate dramatically to meet global climate goals.

The Hydrogen Insights 2024 report

The Hydrogen Insights 2024 report, released today and co-authored by McKinsey & Company, reveals that while the global project pipeline has grown by a factor of seven since 2020 from 228 projects to 1,572 projects, as of May 2024, it has also matured, with a strong focus on advancing projects towards execution. Most notably, clean hydrogen projects that reached FID have also seen a seven-fold increase in committed investment, growing from approximately USD 10 billion across 102 projects in 2020 to some USD 75 billion across 434 projects in 2024.

The most recent data from October 2023 to May 2024 further underscores a clear shift from project planning to implementation. Total announced investments through 2030 have increased by approximately 20% - from USD 570 billion to USD 680 billion. The most notable growth has occurred in the more advanced stages of project development, with investments past FID growing by a remarkable 90%, followed by a 30% increase in front-end engineering design (FEED) stage projects.

This clear shift across the global project pipeline from announcements to implementation is coupled with natural attrition that fosters industry maturation by eliminating less viable projects and prioritising those with the highest potential, a pattern also seen in the early stages of other clean energy industries such as wind and solar.

Jaehoon Chang, President and CEO of Hyundai Motor Company and Co-Chair of the Hydrogen Council, said: "The seven-fold increase in committed capital for hydrogen projects reaching FID over the past four years demonstrates the industry's progress. We are pleased to see the industry walking the talk at this critical transitional moment, as evidenced in the latest Insights report. Moreover, further action is needed to ensure an accessible and affordable hydrogen supply, enabling the widespread adoption of hydrogen."

Despite progress, the hydrogen sector, like other clean energy industries currently, faces macroeconomic headwinds including rising inflation and interest rates, as well as geopolitical tensions affecting energy markets. Sector-specific issues such as regulatory uncertainty and increasing costs for renewable power and electrolysers have led to project delays, particularly for renewable hydrogen projects.

Ivana Jemelkova, CEO of the Hydrogen Council, said: "This report sends a clear message: hydrogen is happening. Now that hydrogen is a reality in the energy transition, it's time to drive significantly more investment by 2030 to meet our mid-century targets. Equipped with concrete lessons learned from the past four years, we must urgently address challenges in key markets and create a more favourable environment for project execution."

Sanjiv Lamba, CEO of Linde and Co-Chair of the Hydrogen Council, said: "Realising hydrogen's full climate and socio-economic potential requires a united effort from governments and industry. With a supportive regulatory framework and targeted incentives, investors will have the certainty they need to move projects to FID - ultimately contributing to achieving global climate targets."

About Hydrogen Insights
Hydrogen Insights is the Hydrogen Council's regularly published perspective on the hydrogen industry's evolution. It summarises the current state of the global hydrogen sector and actual hydrogen deployment. Authored by the Hydrogen Council in collaboration with McKinsey & Company, the report draws on a combination of public information and proprietary data from Hydrogen Council members and represents a collaborative effort to share an objective, holistic, and quantitative perspective on the status of the global hydrogen ecosystem.

About The Hydrogen Council
The Hydrogen Council is a global CEO-led initiative with a united vision and long-term ambition for hydrogen to accelerate the clean energy transition. It brings together a diverse group of 140 companies from 20 countries across Americas, Europe, Africa, the Middle East and Asia Pacific. Spanning the entire value chain, and including large multinationals, innovative start-ups as well as investors, the Council's membership represents some $9 trillion in market capitalization, 6.8 million in FTEs and some $6.4 trillion in revenues.

The Council is committed to unlocking the sustainability potential of clean hydrogen, fostering business and technological innovation as drivers for sustainable growth, creating quality jobs and delivering social value. Using its global reach to promote collaboration between industry, governments, investors, and the civil society, the Council provides insights on and pathways for accelerating the deployment of hydrogen ecosystems around the world. It also supports the development of international safety and sustainability standards, paving the way for the deployment of reliable hydrogen solutions at scale.

To find out more visit?www.hydrogencouncil.com?and follow us on X?@HydrogenCouncil?and?LinkedIn.

Media Enquiries
Joanna Damerell, Communications Manager, Hydrogen Council
Joanna.damerell@hydrogencouncil.com

Photo - https://mma.prnewswire.com/media/2507378/Hydrogen_Insights_2024_report.jpg

Cision View original content:https://www.prnewswire.co.uk/news-releases/global-hydrogen-industry-reports-75-billion-in-committed-capital-but-climate-targets-at-stake-due-to-project-delays-302250196.html

© 2024 PR Newswire
Favoritenwechsel - diese 5 Werte sollten Anleger im Depot haben!
Das Börsenjahr 2026 ist für viele Anleger ernüchternd gestartet. Tech-Werte straucheln, der Nasdaq 100 tritt auf der Stelle und ausgerechnet alte Favoriten wie Microsoft und SAP rutschen zweistellig ab. KI ist plötzlich kein Rückenwind mehr, sondern ein Belastungsfaktor, weil Investoren beginnen, die finanzielle Nachhaltigkeit zu hinterfragen.

Gleichzeitig vollzieht sich an der Wall Street ein lautloser Favoritenwechsel. Während viele auf Wachstum setzen, feiern Value-Titel mit verlässlichen Cashflows ihr Comeback: Telekommunikation, Industrie, Energie, Pharma – die „Cashmaschinen“ der Realwirtschaft verdrängen hoch bewertete Hoffnungsträger.

In unserem aktuellen Spezialreport stellen wir fünf Aktien vor, die genau in dieses neue Marktbild passen: solide, günstig bewertet und mit attraktiver Dividende. Werte, die nicht nur laufende Erträge liefern, sondern auch bei Marktkorrekturen Sicherheit bieten.

Jetzt den kostenlosen Report sichern – bevor der Value-Zug 2026 endgültig abfährt!

Dieses exklusive PDF ist nur für kurze Zeit gratis verfügbar.
Werbehinweise: Die Billigung des Basisprospekts durch die BaFin ist nicht als ihre Befürwortung der angebotenen Wertpapiere zu verstehen. Wir empfehlen Interessenten und potenziellen Anlegern den Basisprospekt und die Endgültigen Bedingungen zu lesen, bevor sie eine Anlageentscheidung treffen, um sich möglichst umfassend zu informieren, insbesondere über die potenziellen Risiken und Chancen des Wertpapiers. Sie sind im Begriff, ein Produkt zu erwerben, das nicht einfach ist und schwer zu verstehen sein kann.