Dutch grid operators TenneT, Enexis, Liander, and Stedin say that expanded use of "capacity limitation contracts" among renewable energy operators could free up about 880 MW of additional grid capacity. The contracts are granted by congestion service providers (CSPs), which act as intermediaries in the Netherlands. Dutch grid operators TenneT, Enexis, Liander, and Stedin released reports this week on available grid capacity, following new requirements from the Netherlands Authority for Consumers and Markets (ACM). "The results of the congestion studies at the regional grid operators provide virtually ...Den vollständigen Artikel lesen ...
© 2024 pv magazine